If you live near a proposed or operating data centre in Australia, you might wonder who decides where these facilities go. You may also wonder who tech executives meet behind closed doors before construction begins. A new report reveals that industry leaders have secured direct access to the country’s most powerful state politicians.
An analysis of data centre lobbying in Australia reveals the scale of access across the country. Bosses at 10 data-centre companies secured 119 meetings with state premiers and ministers in five states and territories over a three-year period. The findings come from a Transparency International Australia report, reported by Guardian Australia and InDaily.
Political donations from major data-centre operators and their contracted lobbying firms nearly tripled during those three years. Donations rose sharply from 685,000 Australian dollars to 1.8 million Australian dollars.
Queensland Premier David Crisafulli was by far the most frequently accessed state premier. Public diaries show Crisafulli held 13 meetings with data-centre executives over the three years.
If a facility is planned near your community, the talks that shaped its approval may never be published. Only five states and territories release ministerial diaries. Federal ministerial meetings remain closed to the public. Australian lobbying laws also do not cover in-house lobbyists or government relations employees. That leaves residents without a complete record of who influenced major project decisions.
State Access And Canberra Appointments
The 119 meetings took place in New South Wales, Victoria, Tasmania, Queensland and the Australian Capital Territory. These jurisdictions alone publish ministerial diaries. Most meetings were held in 2026.
Three companies held the most meetings: Amazon Web Services, Macquarie Technology Group and NextDC. In Tasmania, Firmus Technologies secured 10 meetings with ministers and the premier this year alone. That access came while its expansion faced sustained local backlash.
Premier Crisafulli met NextDC three times in three weeks across August and September. Roughly a month later, NextDC’s Melbourne expansion was halted after power provider pole delays tied to community backlash.
Crisafulli soon announced a framework to fast-track data-centre approvals, removing decisions from local councils. In September, Crisafulli flew to the United States. He secured a 31.9 billion US dollar deal with Anthropic for Australia’s potential largest data centre. His office was contacted for comment.
The report also cited four senior federal public servants quitting to take leadership roles at OpenAI, AirTrunk and CDC. Three moves happened this year.
Clancy Moore, chief executive of Transparency International Australia, called the figures “just the tip of the iceberg.” Moore questioned how many undisclosed meetings occur with federal ministers. He added that Australian lobbying laws do not cover in-house staff, leaving little oversight.
Industry leaders defended the contact. NextDC chair Stephen Flynn said he was “not sure we are great at lobbying as an industry or as a company.” Flynn noted the world had changed. Sally Mackenzie, president of the Australian Professional Government Relations Association, called the engagement a sign of the system working as intended. Mackenzie said: “Lobbying is an important part of the democratic process.” She added: “It ensures that all stakeholders have the ability to communicate with government.”
How many meetings did data-centre companies get? Public diaries show the 119 meetings were secured by bosses at 10 companies across five states and territories over three years.
In summary, major data-centre companies have expanded their access to state leaders while political donations tripled. Attention now turns to Queensland’s proposed fast-track framework for data-centre approvals. Watchers will also follow whether federal lawmakers consider lobbying reforms. Any future changes could bring in-house lobbyists and federal ministerial diaries into the open.